Exponent Engineering and Scientific Services is doing the forensic work to determine the root cause of the fire that happened May 14 at Laramie River Station near Wheatland, WY.

Exponent arrived on plant site May 16 and should complete preliminary work May 17. They have not identified a specific root cause of the fire.

No further significant structural damage has been found. The areas that sustained damage were the breakaway walls and windows in Units 1 and 2 surge bin areas and adjacent areas.

Unit 1 is estimated to return to service June 1. Unit 2 will likely extend its scheduled eight week maintenance outage from its original return-to-service date of May 26 to June 8.

Follow the story
May 14: No injuries at Laramie River Station fire
May 15: Fire damage assessment ongoing at Laramie River Station

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: