May: Dry Fork Station’s milestone month

May was a busy month for employees at the Dry Fork Station. Crews hit one milestone, after another, after another.

It began with the first turbine roll in the early part of the month. Then, after testing and several system checks, the plant was synced to the transmission grid for the first time. That was the first time electricity went outside the plant. Check out Milestone: Dry Fork Station syncs to the transmission grid.

And on May 18, coal, the primary fuel for the plant, was successfully burned in the furnace for the first time. Watch the video.

Crews are now testing all the different systems for maximum efficiencies. It’s all part of preparing Basin Electric’s newest plant for commercial operation.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: